Friday, April 2, 2010


Entrance looks different.















Most exciting, John Hickman and crew started framing in the East master bedroom. We can already tell, the new patio doors and windows will look awesome.










This week, remodel permit in hand, we started demolition work. The insulation has been bundled up ready to be recycled. We were planning on reusing it in the crawl space, but it doesn't make sense to keep moving it during construction.








The exterior stone and siding had to come down right away to allow for the new windows and patio doors to be framed in.


Placing one of the septic tanks.















The septic system has been upgraded to 5 bedrooms. A snowy winter meant this task was stop-and-go. The septic is now ready for inspection.





1st task was winterizing the house to keep weather and critters out -the latter not successful.