The glass railing on the East master deck is finished. The top rail adds a lot of strength and following a windy night prior to installation, we are happy it is now in place.
Kyle of WX Kohler Design is fine tuning the west railing,
while Will installs the top rail on the dining room deck.
Roy was happy to see the Great Room Ipe decking survived being covered for the last few months without damage. This deck is ready for its glass railing too.
While the deer happily munch their lunch below,
new vegetation (hopefully deer-proof) is about to be planted above in the retaining wall.
The Landscape Concepts crew is placing hardy kinickinick and juniper in each grid.
The West Master floor has been prepped for instalation of the plumbing for the bathtub and tub filler.
The West Master bath is nearly finished.
The sinks are prepped and ready for installation.
Tejo and Jake of Matrix Plumbing Inc are prepping the tub and floor for installation in the East Master Bath.
The mirror has been installed also.
The sinks will be the last fixtures to be placed.
Zane has started re-installing the doors in the East Master.
Jeff is installing a smoke detector in the secondary elevator shaft.
Eric of Affordable Trim Installation is installing the stair treads in the East staircase.
It's time to tackle installation of the Great Room Chandelier. Since it came in a large box weighing 400 lbs, we needed a forklift and a lift.
The crate was so large we had to rent a flat bed truck to transport it up to the house.
With the forklift, placing the crate on to the Great Room deck was a piece of cake.