Friday, February 18, 2011

The doors have arrived and Greg and Zane are busy with the installation. It was a bit of a learning curve but now the guys are pros at installing the unique hinging mechanism.














The den cabinets have all been installed.



















Kristen is enjoying working with a bit of a pattern for the den bath walls.














The installer for Gas Products, Inc fired up the fireplaces to verify all connections are as they should be before the stone surround is installed. Here the Great Room unit.




The East Master unit and





The West Master fireplace.

Friday, February 11, 2011

A glorious view on a glorious day.





It's difficult to obtain a good image of the great room patio doors because it's too bright outside.





Greg, Zane & John unpack and install the first Genesis Innovation cabinets in the den/bedroom 5. They look great.









Next the desk area.
Another of Tony's clever inventions. This stand keeps the saw and other tools in easy reach.




Congratulations to Chris on passing his journeyman electrician exam - way to go!!!





























Trevor of RSI is pretty much living in the electronics mechanical room while making sense of the low voltage wires.















Rick is putting the finishing touches on the tile of the west mechanical room so it is ready for the water tanks.



























Kristen is placing the floor tile in the den bath. The photo really doesn't do Kristen or this tile justice.